Additional railway track Luumäki – Imatra

Mälkä Canal Bridge

Mälkä Canal Bridge Bored Pile Wall

LUIMA Project, Hietalankatu AKS, Steel Pile Sheet Pile Wall

LUIMA Project, Muukko Sheet Pile Wall

LUIMA Project, Vuoksenniska Bridge and Sheet Pile Wall
LUIMA Project, Luumäki-Imatra Railway Section Improvement
The LUIMA project involves the construction of bridges and track improvements along the Luumäki-Imatra railway section, including temporary excavations for construction work. This includes the construction of 6 new underpasses, the Mälkä canal bridge crossing the Saimaa canal, and the replacement of culvert pipes. Temporary excavations for bridge abutments utilized temporary sheet pile and steel pile wall systems, supported by various types of anchoring and compression struts. Additionally, a permanent steel pile wall was designed for the Mälkä canal bridge.